Progress on the ONNE & AKAPAJO Bridges - Nigeria

Construction continues to advance on two major bridges within the East-West Project in Port Harcourt, Nigeria, with significant progress across both sites construction.

Each bridge spans approximately 315 meters across 15 supported axes, featuring post-tensioned main girders and a cast-in-place concrete deck slab.

Construction Progress on Site:

ONNE Bridge

All substructure works have been completed. The contractor is currently progressing with the casting and stressing of the concrete girders, alongside the construction of the transverse beams.

 

AKAPAJO Bridge

Construction of the pile foundations has officially commenced, following the successful completion of the initial pile load tests.

 